Water Treatment Plant Upgrade

Fort Frances, Ontario

completeDrinking WaterSCF
Federal contribution
$500,000
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
20172018201920202021
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 19, 2020(actual)
Construction end
Nov 30, 2020(actual)

Against the original forecast

  • Construction start9 months lateforecast Aug 30, 2019

Also in Fort Frances

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46865 in the federal list. How to read these figures.