Back to projects

Water System Upgrades

Springdale, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$94,070
Federal share50%

of $188.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Springdale
Construction start
Aug 23, 2018(actual)
Construction end
Sep 26, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2018

Also in Springdale