Watermain Program - Phase 2

Thompson, Manitoba

completeDrinking WaterCWWF
Federal contribution
$1.5M
$1,500,000
Federal share50%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Thompson
Construction start
Jun 19, 2017(actual)
Construction end
Sep 15, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2017
  • Construction end7 weeks earlyforecast Nov 1, 2017

Also in Thompson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47131 in the federal list. How to read these figures.