Active Transportation for Starrs

Yarmouth, Nova Scotia

completeActive TransportationPTIF
Federal contribution
$61,422
Federal share50%

of $122.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Yarmouth
Construction start
Sep 15, 2017(actual)
Construction end
Apr 18, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2017
  • Construction end6 months earlyforecast Oct 31, 2018

Also in Yarmouth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47197 in the federal list. How to read these figures.