Chittick Avenue Rehabilitation

West Hants, Nova Scotia

completeWastewaterCWWF
Federal contribution
$398,747
Federal share50%

of $797.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Construction start
May 2, 2017(actual)
Construction end
Aug 10, 2017(actual)

Against the original forecast

  • Construction end8 months earlyforecast Mar 31, 2018