Abercrombie wastewater extension

Pictou, Nova Scotia

completeWastewaterCWWF
Federal contribution
$513,609
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Mar 1, 2018(actual)
Construction end
Feb 25, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Feb 1, 2018
  • Construction end5 weeks earlyforecast Mar 31, 2019