Alma springfield estates water and wastewater extension
Federal contribution
$1.1M
$1,128,896
Federal share50%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of the County of Pictou
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Aug 13, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2017
- Construction end8 months earlyforecast Mar 31, 2019
Also in Pictou
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47243 in the federal list. How to read these figures.