Rehabilitation underground infrastructure - pitt and napean
Federal contribution
$2.3M
$2,320,514
Federal share50%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Port Hawkesbury
- Construction start
- Sep 7, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end4 months earlyforecast Mar 31, 2019
Also in Pictou
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47267 in the federal list. How to read these figures.