Village of McAdam Water Control System Infrastructure Improvement

McAdam, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$34,062
Federal share50%

of $68.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of McAdam
Construction start
Mar 8, 2017(actual)
Construction end
Dec 26, 2018(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast May 1, 2017
  • Construction end8 weeks lateforecast Nov 1, 2018