Wastewater Truck Discharge and Lagoon Upgrades
Tuktoyaktuk, Northwest Territories
Federal contribution
$543,750
Federal share75%
of $725.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Hamlet of Tuktoyaktuk
- Construction start
- Dec 1, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction end5 months lateforecast Nov 1, 2019