Back to projects

Addition vehicle for growth of service

Bradford West Gwillimbury, Ontario

completePublic TransitPTIF
Federal contribution
$76,387
Federal share46%

of $167.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 10, 2017
20172018
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Nov 16, 2017(actual)
Construction end
Jan 24, 2018(actual)

Against the original forecast

  • Construction end7 weeks lateforecast Dec 4, 2017

Also in Bradford West Gwillimbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47769 in the federal list. How to read these figures.