Intelligent Transit Technology
Federal contribution
$89,134
Federal share36%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2016
201720182019
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Medicine Hat
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Apr 18, 2019(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Jun 1, 2019
Also in Medicine Hat
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47848 in the federal list. How to read these figures.