Accessible Bus Stop Upgrades
Federal contribution
$105,514
Federal share31%
of $335.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2016
2017201820192020
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Medicine Hat
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2017
- Construction end2 months lateforecast Jan 31, 2020
Also in Medicine Hat
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47850 in the federal list. How to read these figures.