Back to projects

Lethbridge Transit Terminal and Regional Park n Ride

Lethbridge, Alberta

completePublic TransitPTIF
Federal contribution
$2.0M
$2,027,000
Federal share50%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 3, 2016
20172018
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Lethbridge
Construction start
Jan 31, 2017(actual)
Construction end
Jul 31, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Oct 1, 2016
  • Construction end8 months earlyforecast Mar 31, 2019

Also in Lethbridge