Replacement of Existing 30 year old Stationary Generator and Associated Electrical Works at the River Street Sewage Pumping Station
Federal contribution
$35,687
Federal share48%
of $75.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Tweed
- Construction start
- Apr 1, 2018(actual)
- Construction end
- Aug 30, 2018(actual)
Against the original forecast
- Construction start15 months lateforecast Jan 1, 2017
- Construction end3 months lateforecast May 31, 2018
Also in Tweed
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48056 in the federal list. How to read these figures.