Back to projects

Alexander Crescent - Water and Sanitary Sewer Renewal

Saint Andrews, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$89,843
Federal share43%

of $208.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Saint Andrews
Construction start
May 2, 2017(actual)
Construction end
Jul 12, 2017(actual)

Against the original forecast

  • Construction end6 months earlyforecast Dec 29, 2017

Also in Saint Andrews

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48179 in the federal list. How to read these figures.