Edward Street - Water and Sewer Renewal and Extension
Federal contribution
$247,290
Federal share50%
of $494.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Saint Andrews
- Construction start
- May 3, 2017(actual)
- Construction end
- Mar 31, 2019(actual)
Also in Saint Andrews