Back to projects

Installation of Ultraviolet (UV) System - Du Portage Street Lagoon

Caraquet, New Brunswick

completeWastewaterCWWF
Federal contribution
$257,394
Federal share49%

of $521.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Caraquet
Construction start
Jun 18, 2018(actual)
Construction end
Dec 27, 2019(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 28, 2018
  • Construction end4 weeks lateforecast Nov 29, 2019

Also in Caraquet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48211 in the federal list. How to read these figures.