Thompson Avenue and Springwood Court - Sanitary Sewer Renewal and Combined Sewer Separation

St. Stephen, New Brunswick

completeWastewaterCWWF
Federal contribution
$319,298
Federal share48%

of $669.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
20172018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of St. Stephen
Construction start
Aug 28, 2017(actual)
Construction end
Sep 6, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 15, 2017
  • Construction end13 months earlyforecast Oct 15, 2019