Twenty Fourth Street - Storm Sewer Replacement
Federal contribution
$43,193
Federal share50%
of $86.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of McAdam
- Construction start
- Jul 19, 2017(actual)
- Construction end
- Aug 31, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast May 15, 2017
- Construction end3 months earlyforecast Nov 30, 2017
Also in McAdam
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48233 in the federal list. How to read these figures.