Twenty Fourth Street - Storm Sewer Replacement

McAdam, New Brunswick

completeWastewaterCWWF
Federal contribution
$43,193
Federal share50%

of $86.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of McAdam
Construction start
Jul 19, 2017(actual)
Construction end
Aug 31, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast May 15, 2017
  • Construction end3 months earlyforecast Nov 30, 2017