Leclerc Lift Station Cancellation and Looping Study

Grand Falls, New Brunswick

completeCapacity BuildingCWWF
Federal contribution
$5,631
Federal share15%

of $36.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
20172018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
Jun 22, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2017
  • Construction end3 weeks lateforecast May 31, 2018