Harley Hill Reservoir Upgrades
Federal contribution
$96,086
Federal share50%
of $192.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Grand Falls Regional Municipality
- Construction start
- Jun 15, 2017(actual)
- Construction end
- Oct 24, 2017(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2017
- Construction end5 months earlyforecast Mar 31, 2018
Also in Grand Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48244 in the federal list. How to read these figures.