Replace 1 Accessible Van

West Perth, Ontario

completePublic TransitPTIF
Federal contribution
$28,304
Federal share50%

of $56.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Municipality of West Perth
Construction start
Jul 26, 2017(actual)
Construction end
Nov 8, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 30, 2017
  • Construction end5 months earlyforecast Mar 31, 2018

Also in West Perth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48314 in the federal list. How to read these figures.