Replacement of one Handivan Bus
Federal contribution
$43,833
Federal share47%
of $92.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 10, 2017
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Town of Fort Frances
- Construction start
- May 10, 2017(actual)
- Construction end
- Oct 16, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast Mar 1, 2017
- Construction end6 weeks lateforecast Sep 1, 2017
Also in Fort Frances
- Rainycrest Long Term Care Home - HVAC Upgrades and Replacement$2.3M
- Revitalization of the Fort Frances Memorial Sports Centre$2.0M
- Rainycrest LTC Sprinkler System$1.6M
- Construction of Fort Frances Public Library and Technology Centre$955.0K
- Reconstruction of Colonization Road East from Scott Street intersection to just north of 5th Street Intersection$948.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48324 in the federal list. How to read these figures.