Restoration of Sidewalk at Vale Health and Wellness Centre Bus Stop

Port Colborne, Ontario

completePublic TransitPTIF
Federal contribution
$21,569
Federal share45%

of $48.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Port Colborne
Construction start
Apr 1, 2017(actual)
Construction end
May 31, 2017(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 1, 2017
  • Construction end6 months earlyforecast Dec 1, 2017

Also in Port Colborne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48329 in the federal list. How to read these figures.