Promenade Improvements on West St south of Clarence St
Federal contribution
$10,000
Federal share50%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Port Colborne
- Construction start
- Aug 15, 2017(actual)
- Construction end
- Sep 30, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2017
- Construction end2 months earlyforecast Dec 1, 2017
Also in Port Colborne
- Seaway Wastewater Treatment Plant Expansion$7.2M
- Construction of a Multi-Use Health and Wellness Recreation Centre$6.9M
- Watermain Replacement in Port Colborne$2.0M
- Highway 140 - Highway 3 to Niagara Road 23 in Port Colborne$1.5M
- Replacement of 340 meters watermain and 290 meters of sanitary sewers on Janet Street including storm sewer repair, as needed$361.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48333 in the federal list. How to read these figures.