Trail Entrance Point Improvements at Various Locations

Port Colborne, Ontario

completeActive TransportationPTIF
Federal contribution
$15,000
Federal share50%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017201820192020
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Port Colborne
Construction start
Sep 1, 2018(actual)
Construction end
Sep 15, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2018
  • Construction end10 months earlyforecast Jul 31, 2021

Also in Port Colborne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48334 in the federal list. How to read these figures.