Parry Drive Watermain Looping

Quinte West, Ontario

completeDrinking WaterCWWF
Federal contribution
$238,416
Federal share40%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201820192020
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Quinte West
Construction start
Sep 3, 2019(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start20 months lateforecast Jan 1, 2018

Also in Quinte West

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48360 in the federal list. How to read these figures.