Parry Drive Watermain Looping
Federal contribution
$238,416
Federal share40%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Quinte West
- Construction start
- Sep 3, 2019(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start20 months lateforecast Jan 1, 2018