New mixing system for the Trenton Wastewater Plant Sludge Storage

Quinte West, Ontario

completeWastewaterCWWF
Federal contribution
$322,040
Federal share41%

of $790.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201720182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Quinte West
Construction start
Jan 1, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction end12 months lateforecast Mar 31, 2018