Replacement of the aeration pipes in the treatment plant
Federal contribution
$183,700
Federal share50%
of $367.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
2017
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Plessisville
- Construction start
- Nov 28, 2016(actual)
- Construction end
- Dec 15, 2016(actual)
Against the original forecast
- Construction start8 weeks lateforecast Oct 3, 2016
- Construction end15 months earlyforecast Mar 31, 2018