Upgrade to Water Storage Tank Liner - Water Treatment Plant
Federal contribution
$53,911
Federal share50%
of $107.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Red Rock
- Construction start
- Aug 19, 2017(actual)
- Construction end
- Sep 30, 2017(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2017
- Construction end4 weeks lateforecast Aug 31, 2017
Also in Red Rock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48571 in the federal list. How to read these figures.