Rehabilitation of Existing 1500mm Concrete Storm Sewer and Outfall on Armstrong Avenue
Federal contribution
$93,655
Federal share38%
of $244.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Halton Hills
- Construction start
- Jun 21, 2018(actual)
- Construction end
- Sep 1, 2018(actual)
Against the original forecast
- Construction start12 months lateforecast Jul 1, 2017
- Construction end4 weeks earlyforecast Sep 30, 2018
Also in Halton Hills
- Improvements to Glen Lawson Road and Third Line$937.5K
- Transit Service Strategy Implementation and Specialized Transit Services$558.6K
- Installation of New 825mm Stormwater Sewer and Water Quality Treatment Unit on Armstrong Avenue$415.0K
- Maple Avenue Bike Lanes & Multi-Use Path$214.6K
- Credit Valley Trail - Upper Canada College Phase 1$149.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48635 in the federal list. How to read these figures.