Replacement of Hutchings Road Culvert

Rideau Lakes, Ontario

completeWastewaterCWWF
Federal contribution
$3,500
Federal share9%

of $39.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Rideau Lakes
Construction start
Aug 28, 2017(actual)
Construction end
Dec 9, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 12, 2017
  • Construction end5 months lateforecast Jul 13, 2017