Replacement of Hutchings Road Culvert
Federal contribution
$3,500
Federal share9%
of $39.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Rideau Lakes
- Construction start
- Aug 28, 2017(actual)
- Construction end
- Dec 9, 2017(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 12, 2017
- Construction end5 months lateforecast Jul 13, 2017
Also in Rideau Lakes
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48707 in the federal list. How to read these figures.