Assessment and Plan Development for the Town's Storm Water Management to Achieve Full Storm Water System Optimization

East Gwillimbury, Ontario

completeWastewaterCWWF
Federal contribution
$140,993
Federal share44%

of $320.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of East Gwillimbury
Construction start
Nov 3, 2017(actual)
Construction end
May 10, 2019(actual)

Against the original forecast

  • Construction start9 months lateforecast Feb 1, 2017
  • Construction end6 weeks lateforecast Mar 29, 2019

Also in East Gwillimbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48933 in the federal list. How to read these figures.