Feasibility Study and Inspections: Determine specific areas of rehabilitation focus within the wastewater collection system to improve optimization through reduced inflow and infiltration
Federal contribution
$47,946
Federal share48%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Bancroft
- Construction start
- Jul 25, 2018(actual)
- Construction end
- Oct 15, 2018(actual)
Against the original forecast
- Construction start16 months lateforecast Apr 1, 2017
- Construction end2 weeks lateforecast Sep 30, 2018
Also in Bancroft
- Uprading of the Bancroft Waste Water Treatment Plant$3.2M
- The Green Ice Initiative: Accessible and Sustainable Upgrades to the North Hastings Community Centre$1.9M
- Construction of the Faraday Landfill Leachate Management System$778.3K
- North Hastings Community Hub$750.0K
- Air Conditioning Centennial Manor Long-Term Care$625.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48952 in the federal list. How to read these figures.