Feasibility Study and Inspections: Determine specific areas of rehabilitation focus within the wastewater collection system to improve optimization through reduced inflow and infiltration

Bancroft, Ontario

completeWastewaterCWWF
Federal contribution
$47,946
Federal share48%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Bancroft
Construction start
Jul 25, 2018(actual)
Construction end
Oct 15, 2018(actual)

Against the original forecast

  • Construction start16 months lateforecast Apr 1, 2017
  • Construction end2 weeks lateforecast Sep 30, 2018