Back to projects

Rehabilitation of specific wastewater collection system areas identified as priorities by technical Feasibility Study and Inspections Report

Bancroft, Ontario

completeWastewaterCWWF
Federal contribution
$39,653
Federal share24%

of $163.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Bancroft
Construction start
Sep 1, 2019(actual)
Construction end
Nov 15, 2019(actual)

Against the original forecast

  • Construction start2.3 years lateforecast Jun 1, 2017
  • Construction end5 months earlyforecast Mar 31, 2020

Also in Bancroft