Back to projects

First Street South at Main Street South Storm Sewer Relining

Kenora, Ontario

completeWastewaterCWWF
Federal contribution
$26,890
Federal share50%

of $53.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kenora
Construction start
Nov 28, 2017(actual)
Construction end
Dec 8, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Nov 1, 2017
  • Construction end3 months earlyforecast Mar 1, 2018

Also in Kenora