Houghton Road Storm Sewer Relining

Kenora, Ontario

completeWastewaterCWWF
Federal contribution
$107,644
Federal share50%

of $215.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedFeb 26, 2018
2018
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kenora
Construction start
Nov 6, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Oct 18, 2017
  • Construction end4 months earlyforecast Oct 31, 2018