Drewry Drive Sanitary Sewer Relining
Federal contribution
$57,322
Federal share48%
of $120.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Kenora
- Construction start
- Mar 8, 2018(actual)
- Construction end
- Mar 9, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Feb 1, 2018
- Construction end3 weeks earlyforecast Mar 31, 2018
Also in Kenora
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49160 in the federal list. How to read these figures.