Seegmiller Avenue Sanitary Sewer Relining
Federal contribution
$8,779
Federal share47%
of $18.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
The source gives no usable construction span.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Kenora
- Construction start
- Mar 16, 2018(actual)
- Construction end
- Mar 16, 2018(actual)
Against the original forecast
- Construction start6 weeks lateforecast Feb 1, 2018
- Construction end2 weeks earlyforecast Mar 31, 2018
Also in Kenora
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49164 in the federal list. How to read these figures.