Back to projects

Heenan Place Sanitary Sewer Relining - East End

Kenora, Ontario

completeWastewaterCWWF
Federal contribution
$24,332
Federal share50%

of $48.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018

The source gives no usable construction span.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kenora
Construction start
Mar 10, 2018(actual)
Construction end
Mar 10, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Feb 1, 2018
  • Construction end3 weeks earlyforecast Mar 31, 2018

Also in Kenora

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49175 in the federal list. How to read these figures.