Ninth Avenue South #345 to #322 Sanitary Sewer Relining
Federal contribution
$9,258
Federal share46%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
The source gives no usable construction span.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Kenora
- Construction start
- Mar 7, 2018(actual)
- Construction end
- Mar 7, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Feb 1, 2018
- Construction end3 weeks earlyforecast Mar 31, 2018
Also in Kenora
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49177 in the federal list. How to read these figures.