Ninth Avenue South #345 to #322 Sanitary Sewer Relining

Kenora, Ontario

completeWastewaterCWWF
Federal contribution
$9,258
Federal share46%

of $20.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018

The source gives no usable construction span.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kenora
Construction start
Mar 7, 2018(actual)
Construction end
Mar 7, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Feb 1, 2018
  • Construction end3 weeks earlyforecast Mar 31, 2018