First Street North West Dead End Sanitary Sewer Relining
Federal contribution
$11,230
Federal share50%
of $22.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Kenora
- Construction start
- Oct 1, 2018(actual)
- Construction end
- Oct 15, 2018(actual)
Against the original forecast
- Construction start17 months lateforecast May 1, 2017
- Construction end18 months earlyforecast Mar 31, 2020
Also in Kenora