Schedule

AnnouncedMay 24, 2017
ApprovedFeb 26, 2018
2018
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kenora
Construction start
Sep 11, 2017(actual)
Construction end
Dec 8, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2017