Connection of the Loretto area and Weca area water systems in the Township of Adjala Township

Adjala-Tosorontio, Ontario

completeDrinking WaterCWWF
Federal contribution
$74,589
Federal share36%

of $205.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Feb 27, 2018(actual)
Construction end
May 4, 2020(actual)

Against the original forecast

  • Construction start8 months lateforecast Jun 30, 2017
  • Construction end7 months lateforecast Sep 30, 2019

Also in Adjala-Tosorontio

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49312 in the federal list. How to read these figures.