Back to projects

Rehabilitation of High Point Stormwater Pond

Milton, Ontario

completeWastewaterCWWF
Federal contribution
$179,500
Federal share50%

of $359.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Milton
Construction start
Jul 4, 2017(actual)
Construction end
Aug 31, 2020(actual)

Against the original forecast

  • Construction start8 months lateforecast Nov 1, 2016
  • Construction end5 months lateforecast Mar 31, 2020

Also in Milton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49322 in the federal list. How to read these figures.