Rehabilitation of High Point Stormwater Pond
Federal contribution
$179,500
Federal share50%
of $359.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Milton
- Construction start
- Jul 4, 2017(actual)
- Construction end
- Aug 31, 2020(actual)
Against the original forecast
- Construction start8 months lateforecast Nov 1, 2016
- Construction end5 months lateforecast Mar 31, 2020
Also in Milton