Design: Dingman Creek Subwatershed Stormwater Infrastructure
Federal contribution
$102,000
Federal share50%
of $204.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Jun 26, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction end5 weeks lateforecast Feb 28, 2020
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49325 in the federal list. How to read these figures.