Applegate Stormwater Management Facility
Federal contribution
$348,500
Federal share50%
of $697.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
20182019
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction start9 months lateforecast Oct 1, 2016
- Construction end4 months lateforecast Jun 30, 2019