Design and purchase of Organic Rankine Cycle equipment for Power Generation and Waste Heat Recovery Systems & Biosolids Optimization at Greenway Pollution Control Plant
Federal contribution
$2.9M
$2,949,500
Federal share50%
of $5.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2017201820192020
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Jul 25, 2016(actual)
- Construction end
- Mar 30, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2016
- Construction end2 months lateforecast Jan 30, 2020
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49328 in the federal list. How to read these figures.