East London - Sanitary Servicing Study
Federal contribution
$130,854
Federal share44%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
201820192020
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- May 19, 2017(actual)
- Construction end
- Feb 28, 2020(actual)
Against the original forecast
- Construction start8 months lateforecast Oct 1, 2016
- Construction end2 months lateforecast Dec 20, 2019